Fairewinds Associates ENVY Oversight to JFC 12/06/2010
INTRODUCTION
REPORT:
ATTACHMENTS:
ATTACHMENT 1. NRC SCHEMATIC BWR HPCI
INTRODUCTION
Fairewinds Associates, Inc began its contract with the Joint Fiscal Committee (JFC) and the Joint Fiscal Office (JF0) in July 2009 in order to review the progress made by Entergy Nuclear Vermont Yankee (ENVY) toward addressing the challenges identified by Act 189: An Act Relating To A Comprehensive Vertical Audit (CVA) And Reliability Assessment Of The Vermont Yankee Nuclear Facility, and to present ongoing information and analysis regarding reliability issues with Entergy’s Vermont Yankee Nuclear Power Plant. This current report, Fall 2010, is the first requested report in the extension of services of Arnie Gundersen, Fairewinds Associates, Inc, Burlington, VT as consultant to the Legislative Joint Fiscal Committee.
Section 1. Recommendations for Joint Fiscal Committee and the Legislature
Fairewinds Associates, Inc believes that the following items should be implemented, acted upon or fostered:
- Continued monitoring of the Construction Office Building (COB) Well
- Restart extraction wells
- Add additional extraction wells
- Better communication between the Department of Public Service (DPS) and the
Department of Health (DOH) - Entergy should identify and monitor all gamma ports
- Monthly updates for Legislative review from the DPS on the progress of “completed”
action items. - In the event of a license extension, any MOU between the DPS and Entergy must include
objective criteria and should be submitted for technical review by independent nuclear
engineers to assure engineering reliability and technical accuracy prior to signing of any
MOU. - Again, Fairewinds Associates notes that DPS and ENVY have not addressed the July
2010 recommendations created by the Public Oversight Panel. The Panel expressed
concerns regarding ENVY’s lack of a questioning attitude and inadequate allocation of
resources. - Better communication between DPS and Fairewinds Associates
In addition to the above broad recommendations, detailed notifications and recommendations are delineated in the beginning of each subsection
Section 2. Leaks At Vermont Yankee And Their Monitoring
2.1. Tritium Contamination Moves Into Bedrock
Given the fact that the tritium contamination has moved into bedrock, Fairewinds Associates, Inc
recommends continual monitoring of the Construction Office Building (COB) well reported at
least two times per month and continue for the life of the plant. An assessment of this well will
enable the State of Vermont to monitor the progression of the tritium plume containing not only
tritium but also other radioactive isotopes like Strontium 90 and Cesium 137 in order to mitigate
damage to the aquifer and surrounding environment. Contamination of the aquifer is not part of
NRC jurisdiction or required monitoring. This issue is left to the states to assess and monitor.
To Date: On October 8, 2010, the DOH announced that concentrations of tritium significantly
above background were discovered in the former drinking well for the Construction Office
Building (COB). When ENVY took the COB well out of service February 25, 2010, it said it
was a precautionary matter to eliminate a “small possibility” of “cross contamination” from the
groundwater into the well if the well remained in service. [See press release below.] However,
the hydrological COB well test results announced October 8, 2010 suggest that the likelihood of
cross contamination of the well water was more significant than ENVY engineers had estimated.
History: This on-site well is located between the Connecticut River and the former underground
pipe leak that was discovered in January 2010. Unlike the on-site monitoring wells used to track
the movement of radioactive effluent on site that are only 30 to 40 feet deep, the Construction
Office Building (COB) well is 360 feet deep and actually penetrates through the bedrock into the
aquifer. The COB well was one source of on-site drinking water until it was closed as a
precaution on February 25, 2010, and at the time it was closed no tritium had been detected in
that well. ENVY’s February Press release stated that if the well continued to operate, there was
a “small possibility” that its operation would draw tritium into the aquifer and cause “cross contamination”. Thus, even after the well has been turned off, cross contamination is apparently
occurring.
On February 23, 2010 an ENVY press release regarding the contamination of the Construction
Office Building (COB) well stated:
2.2. Tritium Concentration Levels In Water
The tritium discovered in the Construction Office Building (COB) well October 2010 had a
concentration of more than 1,000 pCi/l, which is almost half the European standard of 2,000
pCi/l of tritium in drinking water. For that reason, Fairewinds Associates, Inc recommends that
the monitoring of the COB well continue for the lifetime and clean up the Vermont Yankee
nuclear power plant. While the current EPA limit for tritium in drinking water is 20,000 pCi/l,
some states, like California, are currently discussing much lower limits in light of new data
showing that tritium remains in the body for much longer than scientists originally believed. The
current EPA and NRC regulations regarding tritium levels in drinking water were created more
than 30-years ago prior to newer testing methods and subsequent scientific data.
An email from Dr. William Irwin on October 27, 2010 indicates that ENVY does not plan further
inspections of this well in the near future. Specifically, Dr. Irwin stated:
In Fairewinds Associates, Inc’s opinion the State has the authority to order continued
monitoring. The state of New Jersey has ordered continuing monitoring of the tritium leak at the
Oyster Creek nuclear power plant, an Exelon owned BWR of similar age to Vermont Yankee.
The tritium leak at Oyster Creek already contaminated the surrounding aquifer before it was
uncovered and the site is now undergoing a mammoth tritium extraction project.
Fairewinds Associates would like the Legislative Joint Fiscal Committee to know that the
upward trend in tritium in wells on the site is most disturbing. While well GZ-3, the very first
shallow on-site test well found to contain tritium, had a concentration of only 700 pCi/l when the
investigation first began in January 2010, the concentration has risen dramatically since that
time. Thus, Fairewinds believes that eliminating the testing of tritium in the deep Construction
Office Building (COB) well seems to be counterproductive to monitoring and mitigating any
potential deleterious trends, as history of other on-site wells shows the concentration may be
escalating, not decreasing. The positive finding of tritium in the COB well at 220 feet indicates
that tritium has entered the bedrock and is seven times deeper than anticipated and than
previously measured in the shallow wells, and does not mean that tritium has entered the
groundwater at a depth of 350 feet. This new and unanticipated discovery of tritium in a deep
well indicates that the tritium is moving downward toward the aquifer where its possible removal
and dissipation will be much slower, expensive, and involved process.
On November 29, 2010, tritium was discovered in well GZ-22D at a depth of 60-feet
immediately above bedrock. Concentrations of 500,000 pCi/l were identified near the
abandoned COB well. These high concentrations occurred 150-feet away from the original leak.
That this concentration is at bedrock near the COB well raises even further concerns about
tritium entering the aquifer.
2.3. Extraction Wells For Removal of Tritium And Other Radioactive Isotopes
An Extraction Well is a “well employed to extract fluids (either water, gas, free product, or a
combination of these) from the subsurface. Extraction is usually accomplished either by a pump
located within the well or suction created by a vacuum pump at the ground surface”[1].
Notification: These ongoing leaks are critical Aging Management Reliability Issues. In its
2009-2010 Summary to the JFC, issued in August 2010, Fairewinds Associates, Inc
recommended that at least one extraction well be operated continuously until Vermont Yankee is
dismantled in order to assure that cesium, strontium and any other radioactive isotopes that
remain trapped in the soil do not make further progressive movement toward the Connecticut
River. In addition to continued operation of the tritiated water extraction well(s), Fairewinds
Associates, Inc also recommends that the Legislature instruct the Department of Health to cease
publicizing ENVY information on its State Website, but rather to instruct Entergy to issue the
information in the form of a Press Release so it is clear that such information is an ENVY
opinion is not misrepresented as an official position of the State. Furthermore, in order to
prevent the migration of cesium and strontium to the water table, aquifer, and Connecticut River,
Fairewinds Associates continues to recommend that the extraction well nearest the area of the
initial leak continue to operate until the Vermont Yankee nuclear power plant is
decommissioned, dismantled, and the site is returned to Greenfield status.
Immediately prior to Thanksgiving, on November 23, 2010, the Vermont Department of Health
(DOH) announced on its website that on November 18, 2010 ENVY shut down its tritium
extraction wells. The DOH site stated:
(http://healthvermont.gov/enviro/rad/yankee/tritium.aspx)
Fairewinds Associates observed that since this Entergy notification was posted on an official
State website, various newspapers across the State interpreted the notice to mean that turning off
the extraction wells was approved by the DOH. The headlines from the November 24 Burlington Free Press read, “Vermont Health Dept. says tritium cleaned at nuke plant”. The
New England Cable Network said, “VT Health Dept. says tritium cleaned at nuke plant”, and the
Brattleboro Reformer headline read, “Tritium cleanup finished at VY”. Concernedly, when
did Entergy notify the DOH or the DPS that is was ceasing operation of these critical extraction
wells? Was DOH or DPS notified of this critical operational change prior to the November 18,
2010 cessation date, on that date or not until immediately prior to the Thanksgiving holiday so
that the scientific facts would get lost during the holiday rush and news coverage. Fairewinds
Associates, Inc wants to remind the Legislature that Entergy has exhibited a pattern of sending
out press releases regarding critical safety and reliability issues on Friday afternoons at 5 pm in
hopes of avoiding public and media scrutiny.
In fact, months earlier, ENVY made the decision to shut off the extraction wells based upon how
much water had been removed, rather than how much tritium remained in the soil. Prior to the
discovery of tritium in bedrock, ENVY decided that when it extracted 300,000 gallons of
tritiated water from the soil the extraction wells would be shut down regardless of how much
tritium still migrated across the site. In spite of the new tritium contamination in the bedrock,
ENVY did not revise its earlier decision stop the tritium extraction effort. Neither ENVY nor the
state mandated any criteria regarding the cessation of this critical extraction well.
According to the October 12 edition of Vermont Digger, “Larry Smith, spokesman for Vermont
Yankee, said Entergy will “re-evaluate” whether it should halt the extraction once the
corporation has reached its target extraction total of 300,000 gallons. So far, the company has
pumped 267,000 gallons of contaminated water from the site”
ENVY has planned to end service of the tritiated water extraction wells at the beginning of
December 2010, at which time it anticipated having removed approximately 300,000 gallons of
tritiated water from the shallow surface wells. December 2010 also appears to have been chosen
as a date to close the tritiated water extraction wells in order to avoid any winter freezing issues
in the extraction of the well pipes. In Fairewinds Associates’ opinion a nominal investment by
ENVY would successfully mitigate such tritiated water extraction well pipe freezing issues during
Vermont’s winter weather. In Fairewinds 2009-2010 Summary to the JFC, Fairewinds Associates, Inc recommended that at least one extraction well be operated continuously until the
plant is dismantled to assure that cesium, strontium and other isotopes remain trapped in the soil
and not make further progressive movement toward the Connecticut River or to bedrock and the
aquifer. Moreover, Fairewinds’ recommendation was made in August 2010, months prior to the
October 2010 discovery of tritiated water contamination in the Construction Office Building
(COB) drinking water well.
The October 2010 discovery of tritiated water at a level seven times deeper than previously
indicated confirms Fairewinds’ August 2010 recommendation that ENVY must keep at least one
extraction well running until the plant is dismantled. In fact, due to the recent discovery of 1,000
pCi/l of tritiated in the former Construction Office Building (COB) drinking water well, it now
appears necessary to keep as many extraction wells running as possible until the plant is
dismantled. Whatever tritiated water may be removed from the surface wells is isotopic
contaminated water that will not enter bedrock and threaten the underlying aquifer.
2.4. Additional Monitoring Wells Placed On Site Following Tritium Leak
In addition to its eastward migration toward the river, it appears that the plume of tritiated water
and other radioactive isotopes have migrated further north and is moving downward into bedrock
and toward the aquifer. Fairewinds Associates, Inc recommends that a formal testing schedule
monitoring the on-site plume, Connecticut River fish, and on-site vegetation be conducted for
tritium, strontium and cesium.
Well GZ-13, which was located considerably to the north of the plume in April, is included
within the plume as of September 2010. This evidence shows that the tritium plume widening at
the same time as it is being drawn deeper toward the aquifer as evidenced by the detection of
tritium 200 feet into the bedrock. While, the Vermont Yankee Nuclear Power Plant site contains
numerous other shallow wells that have been drilled to monitor the spread of the tritiated water
from the leak from the Advanced Off Gas (AOG) system that was uncovered in January 2010 the
testing frequency is not adequate to assess plume migration and possible environmental damage.
The Vermont Department of Health (DOH) website[2] is an excellent source for data regarding the
tritium concentration in these sampling wells. The data indicates that tritium concentrations have
decreased near the leak while increasing further away from the leak. For instance, well GZ-3,
the first monitoring well in which the tritium leak was detected in January 2010 had a reading of
700pCi/l in January. Now GZ-3 has readings more than 100,000 pCi/l according to monitoring
data collected at the end of October 2010. Well GZ-10, the monitoring well nearest the leak had
readings of 2,000,000 pCi/l in February 2010, while the October 2010 data shows that GZ-10 has
readings near zero. This change in well concentrations shows that the radioactive plume of
tritium and other isotopes continues to move east toward the Connecticut River.
2.5. New Safety Related Leak in the High Pressure Coolant Injection (HPCI) System
The recently uncovered leak in ENVY’s High Pressure Coolant Injection system (HPCI) is
another Vermont Yankee aging management reliability issue. Fairewinds Associates’ other
significant concern regarding this leak is that the DPS did not notify the DOH of the radiation
leak for three weeks. While it is most likely that all the radiation that leaked from the remained
contained within the reactor building, Fairewinds Associates maintains that statewide protocols
should exist by which the DOH, which is tasked with the radiation monitoring of Vermont
Yankee, is always made aware of any and all leaks at ENVY. Such protocols should be put in
place from this point forward given ENVY’s aging management reliability issues.
On September 24, 2010 an auxiliary operator noticed steam coming from a pipe in ENVY’s
HPCI. According to records, The Department of Public Service State Nuclear Engineer was
notified of the HPCI leak on September 27, 2010. Almost one month later, on October 19, 2010,
independent sources notified Fairewinds Associates of the HPCI leak. At that time, Fairewinds
Associates’ Chief Engineer Arnie Gundersen requested that the DPS engineer look into the
reported problem and was assured that DPS would investigate. On October 20, the DPS
engineer confirmed to Fairewinds Associates that a leak in the HPCI system had indeed
occurred. DPS had already been aware of the HPCI system leak for three weeks, but did not
notify the Department of Health regarding the existence of the leak until October 20, 2010. Both DOH and Fairewinds Associates, the JFC consultant, had been unaware of the leak for almost a
full month, although NRC had been notified early on as had DPS.
After Fairewinds Associates and DOH were notified of the HPCI leak, NRC Region 1
spokesperson Neil Sheehan issued the following statement:
The system and the drain line are located inside the reactor building. As such, any leakage is captured by a sump and sent to a radioactive liquids treatment system.
The company apparently needed to time to develop a repair plan. It also would have prioritized the work based on the safety significance. It was -- and is -- low in this case.
Entergy attempted to repair the leak on Oct. 6 and could not get good steam isolation on the system without going into the steam tunnel. Therefore, the company decided to halt the effort and rescheduled it for Oct. 15. On Oct. 15, they found it was not a weld that was leaking but that a through-wall hole (pinhole leak) had developed and a different repair plan would have to be put together.
Our Resident Inspectors at Vermont Yankee have stayed on top of the issue and will continue to monitor the company's repair efforts.”
According to Entergy and the NRC, while the leak was releasing radioactive steam and water into the reactor building, none of that radiation is reaching the environment because it is both collected and treated inside the reactor building. Fairewinds believes that the significance of the HPCI leak is that it is located in a Safety Related System (SRS) used to cool the plant in an emergency. High Pressure Safety Related piping is subject to more stringent design, construction, and inspection requirements, therefore it is critical that piping defects in Safety Related Systems should be identified prior to leaking. According to the NRC:
Before a possible cause of the leak was even analyzed, the State’s DPS engineer stated that the
leak in the pipe was due to “erosion”[4]. It is the opinion of Fairewinds Associates, Inc that it
would be technically impossible for “erosion” to cause this leak since the leak is in a one-inch
drain line containing stagnant water, and therefore the pipes would not be subject to the effects
of erosion because the water is stagnant, not moving, and not eroding. Once again, it is
Fairewinds Associates’ belief that this is another Vermont Yankee reliability issue due to aging
management. The industry record substantiates such an opinion where leaks of this type are
generally age related and corrosion induced. A similar one-inch pipe with stagnant water in the
Reactor Water Clean-up system leaked in 2009. Moreover, because stagnant water cannot cause
erosion, Fairewinds believes that corrosion[5] due to stagnation is the most likely cause of the hole
in the HPCI. While, the Public Oversight Panel also identified problems in the Flow Accelerated
Corrosion program due to improper use of Line Correction Factors, it is unlikely that flow
accelerated corrosion would be the cause of this leak since there is no flow in this stagnant pipe.
In its first report issued to the Legislature in March 2009, the Public Oversight Panel identified
that the Vermont Yankee Nuclear Power Plant has experienced Microbiologically Induced
Corrosion (MIC) in its Service Water System, and this issue has also been discussed in previous
Fairewinds Associates’ reports. However, the Service Water System uses unpurified
Connecticut River water while the HPCI system uses purified water, so MIC is an unlikely cause
of this newly discovered leak.
In order to fully repair the leak, ENVY had to make the system “inoperable” while repairs were
made, and since the HPCI is a safety system, this means that other systems must be ready in the event of an accident. The NRC allows this particular safety system to be made “inoperable” for
a short amount of time in order to make emergency repairs. If, after the seven-day allotted time
span for the repair, the repair has not been completed, then ENVY would have to shut down the
plant until the repair is completed. In fact when the plant was shut down in order to repair the
feedwater system leak (see below), ENVY also fixed the HPCI leak.
2.6. Another Feedwater System Leak
Notification: The recent (November 2010) leak in Vermont Yankee’s feedwater systems is
indicative of a systemic issue within Entergy’s aging fleet of nuclear power plants. “Limited
resource allocation for non-safety systems might, therefore, be systemic within Entergy,”
according to the July 2010 final report of the Vermont Yankee Public Oversight Panel.
Fairewinds Associates, Inc recommends that Entergy identify and monitor all gamma ports and
plugs given this systemic aging management reliability issue at old plants like ENVY and
Entergy Nuclear Indian Point. Gamma ports are holes that were used during construction to
inspect pipe welds and were subsequently plugged. After construction, the holes are plugged by
welding over them, and then they are abandoned.
On November 7, 2010 an operator noticed water leaking from a large, 24-inch Feedwater pipe.
Vermont Yankee decided to shut the plant down to repair this leak. According to a Vermont
Yankee press release:
Fairewinds Associates notes that this is the second leak in the feedwater system since 2009. The
location of this latest feedwater leak was in an old “gamma port” in the feedwater pipe. In
January 2009, a different old “gamma port” in feedwater pipe leaked in a similar fashion. As a
result of our questions, DPS contractor NSA informed Fairewinds Associates that these are the
first two-gamma port plugs at Vermont Yankee determined to be leaking.
In 2009 and again in 2010, the radioactive leakage from these “gamma plugs” was captured
within the buildings and properly treated as radioactive waste. Unlike the tritium leak, these two
feedwater leaks did not release unmonitored radiation into the environment.
While the feedwater system contains high pressure, high temperature radioactive water, the NRC
does not consider it to be “safety related.” However, in July 2010, the Public Oversight Panel
expressed its concerns about whether ENVY is allocating enough resources to these reliability
systems that are not safety related. On page 9 of the Supplemental Report of the Public
Oversight Panel Regarding the Comprehensive Reliability Assessment of the Vermont Yankee
Nuclear Power Plant, July 20, 2010, the Public Oversight Panel stated:
In its 2009 report, the Panel noted that inadequacy of available resources for nonsafety related systems probably contributed to the cooling tower collapse in 2007 and leakage in 2008. The Panel is concerned that, one year later, inadequate application of resources continues to plague some non-safety systems, this time the AOG system. In its 2009 report, the Panel said,
In its supplemental report, the Public Oversight Panel also stated that:
The issue of inadequate application of resources takes on heightened importance given Entergy’s status as an aging plant. Over the remainder of Entergy’s operating life, the possibility of shutdown within a few years can never be ruled out and will become a near certainty at some point.”[6] [Emphasis added]
2.7. Act 189 And Review Of ENVY’s Feedwater System Reliability
Notification: Fairewinds Associates, Inc notifies the Legislature that the NSA Report[7] missed
identifying inspection problems that appear to be endemic throughout the feedwater system and
the resulting reliability failure that has resulted in two leaks in 22-months.
Fairewinds Associates has not uncovered any record of periodic inspection of any piping
segment plugs that were abandoned in place after being used in construction. Fairewinds
Associates, Inc recommends that periodic inspection of such piping systems be undertaken in
order to assure ENVY’s reliability due to its aging management reliability issues.
The Vermont legislature specifically chose ENVY's feedwater system as one of the reliability
systems to be evaluated by the DPS contractor NSA. It appears that the NSA report to the
legislature missed this reliability issue that has resulted in two leaks during the past 22-months.
Since January of 2009, ENVY's reliability has been adversely affected by two leaks in the VY’s
feedwater system. Both leaks appear to be linked to "gamma ports" used during construction. In
a review of the December 2008 NSA report to the Legislature, Fairewinds Associates was not
able to find any discussion or reliability assessment of leaky gamma ports in the feedwater
system nor in any of Vermont Yankee’s large bore pipe system. While the Feedwater portion of
the report contains a section regarding inspection, it does not investigate possible leaks in the
feedwater system that may be undetected until openly leaking and the adverse impact of such
undetectable leakage upon plant reliability.
2.8. NRC Root Cause Analysis Of Vermont Yankee’s Tritium Leak
Notification: Fairewinds Associates, Inc wants to inform the Legislature that both the NRC and
ENVY’s root cause analyses of the tritium leaks are inadequate. The Public Oversight Panel
Supplemental Report had a more thorough analysis in which it determined that the lack of a
questioning attitude and inadequate resources were in fact the root cause of the tritium leaks.
Notification: Fairewinds Associates, Inc notes that if aging problems caused the tritium leaks
and aging problems caused the gamma plug leaks, then the effectiveness of ENVY’s aging
management program is not adequate to assure Vermont Yankee’s ongoing reliability.
The cause of the ENVY’s January 2010 tritium leak was reviewed and analyzed by the NRC,
and a report delineating the analysis and the NRC issued its review of the causes on October 13,
2010.
Background: The tritium leak that was first detected during the winter of 2010 was not a single
failure of any one component, but rather a larger breakdown of many components. Beginning in
2007, two separate Advanced Off Gas (AOG) system pipes leaked steam and water into a closed
concrete vault during an extended time period. That concrete vault, which was designed and
constructed during the early 1970’s, had a special drain line with which to collect any leakage.
However, that drain line was most likely clogged with dirt since its construction during the
1970’s and in fact it may never have worked as designed. Since the drain was plugged, the
concrete vault filled with radioactive water containing tritium, cesium, strontium, and cobalt that
then leaked out near a wooden two by four that had also been left since the early 1970’s.
In its October 13, 2010 Inspection Report evaluating the “Root Cause” of the AOG (Advanced
Off Gas System) tritium leak detected in January 2010, the NRC determined that the root cause
was due to construction techniques applied during the 1970’s. NRC said,
Fairewinds Associates notes that the entire power plant was originally constructed at the same time as the AOG (Advanced Off Gas System) vault that leaked and therefore was built to the same 1970 construction standards and 1970 housekeeping standards as the AOG vault. In Fairewinds opinion, it is disingenuous to suggest that the problems associated with the vault might not be found elsewhere in this nuclear plant. Indeed, as has been previously discussed in this report, during November 2010 a gamma plug failed in the feedwater system. Another gamma plug in the feedwater system also failed in January 2009. The failures of these plugs were related to poor weld seals, these aging plugs were also installed in the feedwater piping during the early 1970’s.
Section 3. Progress On Act 189 Reliability List
3.1. What Is The Definition Of Complete?
Notification: While some goals have actually been achieved, on larger efforts “complete” only
means that the DPS contractor, NSA, believes that ENVY has created a process by which to
achieve the goal at some point in the future. Fairewinds Associates, Inc recommends
mandatory, monthly updates by DPS on each of the 90-items delineated by the Public Oversight
Panel in response to Act 189.
Monitoring of these “closed” items means that the State’s Nuclear Engineer is not only
responsible to assure ENVY continues to meet its performance metrics, but that there will no
longer be review meetings by which to assure that ENVY is indeed meeting standards the
legislature set in place in order to assure ENVY’s reliability. For those items that the State
Engineer has responsibility for monitoring, NSA or other experts will only be involved from this
point forward if the State Engineer believes it is necessary.
Before the Legislature reconvenes in January 2011, the DPS, its consultant NSA, and Vermont
Yankee's staff set a goal of “closing” all 81-items identified in the original NSA report as well as
completing review of the additional 9 items from the supplemental AOG (Advanced Off Gas
System tritium leak) inspection. Monitoring of these “closed” items means that the State’s
Engineer is the only person reviewing the 91-items outlined as critical reliability issues by the
Vermont Yankee Public Oversight Panel. The DPS will no longer hold review meetings by which to assure that ENVY is indeed meeting standards the legislature set in place in order to
assure ENVY’s reliability. For those items that the State Engineer has responsibility for
monitoring, NSA or other experts will only be involved from this point forward if the State
Engineer believes it is necessary. Given the critical engineering nature of these issues,
Fairewinds Associates, Inc recommends ongoing oversight of this process by an independent
party in conjunction with the DPS.
While the DPS goal of “closing” ENVY’s list of repair items has been achieved,
Fairewinds Associates would like the Legislature to be informed that the term “closing” as
applied to the list of 90-items does not mean that any actual task has been accomplished or fully
completed, and in Fairewinds Associates’ opinion, such action does not fulfill the mandate of
Act 189 or assure Vermonter that ENVY’s aging management reliability issues have been
rectified.
3.2. Procedure Upgrades
Notification: Only 10 percent of all procedures necessary for the effective operation of the
Vermont Yankee nuclear power plant have been updated and revised. ENVY remains severely
behind on this critical item, and the only person overseeing this process is the DPS engineer.
One area of critical concern to the Public Oversight Panel is the improvement of ENVY’s
operating procedures. The Public Oversight Panel determined that procedure upgrades were
critical due to ENVY’s aging employees who are beginning to retire. Revised procedures were
deemed necessary to transfer knowledge between VY’s older staff and personnel who would run
the plant for the next 20-years if it is relicensed. There are about 875 procedures that need to be
rewritten. ENVY chose to rewrite 220 procedures in its "Phase 1", and those 220 procedures
were to have been rewritten by September 2010. In actuality, ENVY has only completed the
procedure writing on 70-procedures. The new goal agreed upon by DPS and ENVY is that the
initial 220 procedures will be completed and approved for use sometime during the first quarter
of 2011. Recently ENVY hired three contractors to assist in procedure writing to meet this new
goal. So, although only 10 percent of ENVY’s critical operating procedures have been rewritten
and approved, the procedure upgrade process has been approved by NSA and therefore the requirement has been reclassified as closed and color-coded Blue, meaning that no further action
is required except for monitoring by the DPS State Engineer.
3.3. Staffing Levels
Notification: The number of on-site personnel has declined by at least 22-employees between
January 2010 and September 2010; just as the plant has been facing reliability issues and leaks
that require more personnel, not less.
In September, Fairewinds asked the State’s Engineer to investigate a troubling trend in staffing at
VY that he is responsible for monitoring. Fairewinds identified to the State’s Engineer that
personnel in the "Site Cost Center" have decreased from 609 in January to 587 at the end of
September. While the State’s Engineer promised to investigate, there has been no response to
Fairewinds query almost two months later. This is an area of concern that was also identified by
the Public Oversight Panel. See “Cooperation” Section below.
3.4. Microbiologically Induced corrosion (MIC)
At the end of September, the plant’s MIC index showed that 77 percent of the plant is experiencing MIC. Specifically, plant data shows that the MIC index as 23% green (good), 17% red (bad), and 60% yellow (concern). Again, the State Engineer is responsible for monitoring these trends.
3.5. Condenser
Most nuclear power plants replace their condenser at between 20 and 30 years of continued
operation. Vermont Yankee’s condenser has lasted 39-years. Condenser leaks adversely affect
reliability and the water quality of the water that is used inside the nuclear plant as the primary
reactor coolant. The earliest that ENVY plans to replace this aging Condenser is 2016.
Condensers have been known to fail catastrophically, as occurred at Entergy’s Grand Gulf Plant
shutting down the plant for several months. Thus failure of the Condenser would have a
deleterious impact upon Vermont Yankee’s overall reliability. In previous hearing testimony, Fairewinds Associates noted that rather than invest $200,000,000 (in 2016 dollars) in a new
condenser, Entergy may choose instead to shut down the plant. If the price of electricity does
not rebound, it would be difficult to recoup such a large investment during the final years of the
plant’s life.
3.6. Public Oversight Panel Supplemental Recommendations
Finally, Fairewinds notes that the DPS and ENVY have not acted upon the Public Oversight Panel’s recommendations presented in their July report to the Legislature. The panel noted that the plant staff lacked a questioning attitude and the ENVY was not providing adequate resources to improve Vermont Yankee in a timely fashion. The recent example of the “gamma port” failure in the feedwater system indicate both a lack of a questioning attitude and the fact that insufficient resources are being applied at VY on areas of reliability concern.
3.7. Degraded Reliability in 2010
There have been three Unplanned Shutdowns Since May 2010. The Public Oversight Panel’s supplemental report also acknowledged that between ENVY’s Fall 2007 refueling outage and its November 2009 refueling outage, VY had a “breaker to breaker” run of 530 days without a shutdown. After reviewing the historical record, Fairewinds has determined Vermont Yankee ended its latest refueling outage on May 24, 2010, at which time Entergy issued a press release that stated:
On May 26, 2010, the plant tripped off line and Entergy released the following press release:
After repairs were made, Vermont Yankee started back up once again on May 29. As it’s nuclear chain reaction began to generate steam and the off gas system was placed in service again, operators noticed a new leak and once again shut the plant down. Entergy issued the following press release:
This was a new leak. The leak has been stopped and there is no leak at this time.
There is no threat to public health or safety.
The vapor and water dripping was identified at approximately 730 pm during warm up of the AOG system.
No leakage was visible after warm up and shortly after the AOG system was placed in service.
The leak has been located on a two-inch drain line and is approximately one eighth of an inch in diameter.
The vapor and water dripping was observed coming from the end of a concrete enclosure surrounding a two-inch drain line in the AOG excavation just before the pipe enters the wall of the drain tank room.
Soil testing of the area has been performed and tested positive for several radioisotopes in a one-foot radius from the leak source.”
Once again, after this leak was repaired, the plant started up again and ran for 163 days before shutting down once again because of a leak in the feedwater system on November 7, 2010. Entergy issued the following press release at that time:
The NRC Resident Inspector has been informed of the issue and of the plan to remove the station from service. The plant had been operating at reduced power for a scheduled rod pattern adjustment and to support line work by Public Service Company of New Hampshire. The plant had been on line for 163 days of continuous operation.”
The NRC usually applies increased inspection attention to reactors that shutdown unexpectedly three or more times in 7,000 hours. However, the NRC has decided that since these additional shut-downs did not occur while VY was operating at full power, it will not provide additional inspections until VY shuts down two more times.
Section 4. Cooperation Between The DPS And Fairewinds Associates, Inc
The Department of Public Service and its state nuclear engineer are tasked with monitoring
ENVY’s progress on a variety of issues, including but not limited to its compliance with
Legislative Statue Act 189. Fairewinds Associates, Inc specifically wrote to the DPS state
engineer requesting progress graphs that the DPS is required to monitor. Incredibly, the DPS
wrote back that it does not have any ENVY progress graphs. If the DPS is unable to answer
these reliability issues, then ENVY is not receiving the requisite oversight Act 189 required in
order to ascertain and assure ENVY’s continued operating reliability. Such oversight is
especially critical given the DPS decision to designate unfinished items as complete.
The following exchange is the most recent example of communication difficulties. These
requested graphs include the staffing issues that are required post Act 189 monitoring issues.
Sent: Monday, November 29, 2010 8:38 AM
To: Vanags, Uldis
Subject: copies
Hi Uldis,
May I have copies of the performance graphs that are posted on the wall outside Mike
Coulomb's office? I believe they are updated monthly, so as they are updates, would you
send those along each month.
Thanks, Arnie
Hi Arnie: I don't have copies of the performance graphs outside of the nuclear
station. Please submit your information requests to Mike McKenney at Vermont
Yankee so they can process it.
I sent you Mike's contact information earlier but if you can't locate it I will be
glad to send it to you.
Hope you had a good holiday,
Uldis
Uldis Vanags
State Nuclear Engineer
Vermont Department of Public Service
112 State Street
Montpelier, VT 05620-2601
Date: November 30, 2010 4:23:48 PM EST
To: "Vanags, Uldis" "Hofmann, Sarah"
Subject: Re: copies
Uldis, Thanks for replying. Arnie
In order to fulfill its consultancy role to the Joint Fiscal Committee, Fairewinds Associates, Inc
has asked appropriate questions of the DPS and believes is not receiving adequate or appropriate
answers in reply. The evidence and job description show that in its oversight role as the state
agency designated with monitoring the operation of Vermont Yankee, the DPS should know the
answers to the questions Fairewinds Associates, Inc is asking, but the DPS engineer instead has
attempted to make this issue a jurisdictional issue among the Legislature, Fairewinds Associates,
Inc, and Entergy Nuclear Vermont Yankee. After refusing to answer two questions from
Fairewinds Associates, the DPS claimed it would reply to Fairewinds Associates’ third question
in a timely manner, but as of the publication of this report, DPS still has not responded.
In October, Fairewinds made the following request of the DPS:
Sent: Wednesday, October 20, 2010 9:16 AM
To: Vanags, Uldis; Hofmann, Sarah
Subject: keep me informed about...
Hi Uldis
I would like to be kept informed about:
- The cause of crack/leak in the HPCI and when VY enters an LCO
condition. Generic Letter 91-18 Supplement 1 established the agency's
expectations for determining when degraded conditions do not render a
system inoperable. It covers things like missing a required surveillance
test and when in-plant discoveries reveal a component to be other than as
designed. - Can you confirm that VY followed this guidance and provided
reasonable engineering judgment that the leaking weld would not impair
the safety function of the HPCI system throughout the entire length of
that safety mission? If 91-18 was properly applied, HPCI could be
operable now, but would become inoperable when workers cut into the
pipe for the repairs to the weld. That analysis would also have to
consider the pre-existing leak of radioactive fluid into either primary
containment (if the leaking weld is inside the drywell) or secondary
containment. Most safety analyses assume a leak of up to 25 gpm of fluid
containing the post-accident source term into the secondary containment
for worker and EQ doses.
In response, the DPS sent the following email to Fairewinds:
Date: October 20, 2010 2:56:21 PM EDT
To: 'Arnie Gundersen' "Hofmann, Sarah"
Subject: RE: keep me informed about...
Hi Arnie: I read over the information request you have below, and while I enjoy
discussing these topics with you when we get together, I feel that the first two questions
concerning the HPSI would be better addressed by Vermont Yankee. If you remember in
your JFO capacity the Department does not serve as "middleman" as it did with the POP.
Please see the email I pasted below for the address to whom to send your questions. I will
answer your third question about the staffing which I discussed with the NSA folks.
Uldis
Sent: Monday, March 15, 2010 2:23 PM
To: 'Arnie Gundersen' Cc: Hofmann, Sarah; Cotter, John; 'McKenney, Michael P'; McCann, John
Subject: Process to submit questions to Vermont Yankee
Arnie: As I mentioned at the RIC, questions to Vermont Yankee via your JFO
capacity need to be submitted to the plant directly by you. I discussed this with
John McCann and he stated that questions are to be submitted in letter form
mailed to Michael McKenney, Acting State Liaison Engineer, and copied to
Michael Colomb, Site Vice President.
The address is:
Acting State Liaison Engineer
Entergy Nuclear Operations Inc.
Vermont Yankee Nuclear Power Station
320 Governor Hunt Road
Vernon, Vt. 05354
Let me know if you have any questions. Uldis
During the September and October meetings among the Act 189 consultants at Vermont Yankee, which Mr. Gundersen attended, note was made regarding the tracking issues that the DPS engineer must continue in his ongoing responsibility to make sure ENVY is implementing the corrections determined by the Vermont Yankee Public Oversight Panel. The questions asked by Mr. Gundersen all pertain to the specific issues regarding Vermont Yankee’s aging management and reliability. If the DPS is not able to answer these reliability issues, then ENVY is not receiving the requisite oversight Act 189 required in order to ascertain and assure ENVY’s continued reliable operation. Fairewinds Associates, Inc believes such oversight is especially critical given the DPS decision to designate unfinished items as complete.
Endnotes
- http://www.contaminatedsite.com/glossary/glossary%20-%20e.htm, Contaminated And
Hazardous Waste Site Management Glossary, Gowen Environmental. - http://www.healthvermont.gov/enviro/rad/yankee/documents/VYTritiumData.pdf
- Reactor Concepts Manual, Boiling Water Reactor Systems, USNRC Technical Training Center 3-13 Rev 0200,
http://www.google.com/url?sa=t&source=web&cd=8&ved=0CD0QFjAH&url=http%3A%2F%2Fwww.nrc.go
v%2Freading-rm%2Fbasicref%
2Fteachers%2F03.pdf&rct=j&q=%20%20high%20pressure%20coolant%20injection%20system&ei=3L
LJTOXmEYOC8gav1LH0Cg&usg=AFQjCNEW
LKzczHbUs9S8iz2NBxH9sbSnw& sig2=BB8r94JPS4o6MBSbMKlssg - Erosion - gradual wearing away of the Earth by wind or water; disintegration; deterioration
http://dictionary.babylon.com/erosion/ - Corrosion - wear, deterioration; rust, oxidation http://dictionary.babylon.com/corrosion/
- Supplemental Report of the Public Oversight Panel Regarding the Comprehensive Reliability
Assessment of the Vermont Yankee Nuclear Power Plant, July 20, 2010, Page 10 - NSA – Nuclear Safety Associates – The Contractor hired by DPS to conduct the Act 189 Audit.